I. Comprehensive data review and gap identification for groundwater modeling and integrated water resources management

Client:

Period: April 2024 to April 2025

Role: Project Manager

II. Study of calculating water consumption for agricultural irrigation purposes from all water sources used in the Kingdom (Qias 2)

Client: Saudi Irrigation Organization (SIO)

Period: January 2023 to June 2024

Role: Project Manager

III. Irrigation SCADA evaluation and water loss calculations

Client: Saudi Irrigation Organization (SIO)

Period: September 2020 to August 2021

Role: Project Manager

IV. Environmental & social impact assessment for the construction and operation of an offshore recreational facility (THE RIG) in the vicinity of Juraid Island, Arabian Gulf. https://therig.sa/https://therig.sa/

Client: Oil Park Development Company (OPDC)

Period: January 2023 to August 2023

Role: Task Leader – Water Consumption Management Study

V. Environmental impact assessment for Safaniyah offshore oil and water injection facilities

Client: Worley, Saudi Arabia

Period: June 2022 to November 2022

Role: Task Leader – Water System Optimization

VI. Environmental impact assessment for Manifa crude oil and water injection facilities

Client: KBR-AMCDE, Saudi Arabia

Period: June 2022 to April 2023

Role: Task Leader – Water System Optimization

VII. Environmental impact assessment for Marjan gas lift facilities

Client: Worley, Saudi Arabia

Period: June 2022 to February 2023

Role: Task Leader – Water System Optimization

VIII. Environmental impact assessment for Ras AlKhair offshore terminals

Client: Saudi ARAMCO

Role: Task Leader – Water System Optimization

IX. Continuous power factor management between the consumer and service provider (Phase 1)

Client: Water & Electricity Regulatory Authority (WERA), Saudi Arabia

Period: June 2019 to July 2020

Role: Task Leader – Data Analysis and Tariff Modeling

KFUPM funded


I. Nondestructive testing using Electromagnetic Acoustic Transducer (EMAT)

Period: February 2020 to December 2020

Role: P.I.

II. Feasibility study on Aquaponics farm for food security, sovereignty, and purity in regions like Saudi Arabia

Period: April 2020 to April 2023

Role: Co-I

III. Leakage current-based contamination level monitoring of high voltage insulators

Period: April 2021 to September 2022

Role: Co-I

Rosen (Germany & Saudi Arabia)


I. Defect detection with EMAT sensors for ARAMCO pipelines

Period: June 2018 to January 2019

Role: Team lead

II. Feasibility study for inline inspection of pipelines with challenging fluids

Period: June 2016 to May 2018

Role: Team lead

III. Development of LabVIEW-based 4D-scanner program for automatic scanning and its integration with ultrasonic DAQ system

Period: January 2016 to May 2016

Role: Task leader